RENEWABLES PROJECT
Greater Gabbard OWF
JUMBO JAVELIN | UNITED KINGDOM
The scope of work comprised of the Transport and Installation of 131 Transition Pieces onto pre-installed Monopiles, including the levelling and grouting. Each trip the Jumbo Javelin loaded nine 280t TP’s including the associated grout quantity. At location each TP was placed onto the Monopile in a specified orientation and levelled to its final position. To fixate the TP, the annulus was filled with grout.
Download the Greater Gabbard Offshore Wind Farm project specifications.